Lynnwood Crossroads update: businesses should be open by November

sitework

The site work at Lynnwood Crossroads Shopping Center is close to being substantially complete.

Ninety percent of the paving is finished, all of the light poles are in, and the landscaping will be installed within the next few weeks.

LA Fitness has completed all of its exterior walls and roof structure. The two corner buildings are progressing with the steel structure which will house Starbucks, Great Clips and Qdoba in building one with Five Guys Burgers, Yogurtland, Best Sushi & Teriyaki and Verizon in building two.

The construction on pad three of Hop Jack’s Restaurant is expected to begin in September. Look for the first business to be open by November.

 